Changes for page R21 Docker - Double Lane

Last modified by Erik Bakker on 2026/06/16 11:56

From version 15.1
edited by Erik Bakker
on 2023/09/13 07:27
Change comment: There is no comment for this version
To version 33.1
edited by Erik Bakker
on 2026/06/15 09:37
Change comment: There is no comment for this version

Summary

Details

Page properties
Title
... ... @@ -1,1 +1,1 @@
1 -R11 Docker - Double lane
1 +R21 Docker - Double Lane
Content
... ... @@ -1,24 +1,21 @@
1 -Service affecting R11 template that improves stability of AWS EFS mounts in running instances when a reconnect to EFS is triggered.
1 +{{info}}This environment template needs to be applied on all environments of all (your) models before August 15th, 2026{{/info}}
2 2  
3 +**Non-service affecting** final template to use the **R21** double lane release. This is the only step for your upgrade to the new **R21** template.
4 +
3 3  **Process**
4 -We upgrade in two steps to use the new R11 release of the cloud template. Of these two steps, the intermediate step is non-service affecting, and the final step is service affecting.
6 +We upgrade in one step to use the new **R19** release of the cloud template. This step is non-service affecting.
5 5  
6 6  **Overview**
7 -It improves the stability of the AWS EFS mounts in running instances when a reconnect to EFS is triggered.
9 +* Upgrade cloud environment to prepare for IP address migration.
10 +* Update authorization server to enable future certificate rotations.
8 8  
9 -**Updates**
10 -* Updated mount configurations of EFS to adhere to provider's standards.
11 -* Ubuntu version update including latest security patches.
12 -* This upgrade is service-affecting, as all instances have to be recreated.
13 -
14 14  **Update Steps**
15 -* Use the intermediate template (non-service affecting) (duration: 10 minutes)
16 -** This step will upgrade the backup machines hosted in the second Availability Zone in your Cloudslot.
13 +* Use the final **R19** template (non-service affecting) (duration: 10 minutes)
14 +** This step will upgrade the backup machines hosted in the second Availability Zone in your cloudslot.
17 17  ** The network drive containing the Artemis queue store and your Elastic IPs will remain.
18 -* Use the final template (non-service affecting) (duration: 10 minutes)
19 -** This step will update your cloud slot configuration to allow an MQTT broker with failover settings.
20 -* User actions after applying the final template:
21 -** Check if all runtimes are reachable by Deploy Architecture.
22 -** Check if all flows have been installed according to the active release.
23 -** Check if messages pass through the model by verifying a critical message flow in external systems.
16 +** The runtimes on the machines will be restored using the active release in the eMagiz portal
17 +* User actions after applying the intermediate template:
18 +** Check if all ".02" runtimes are reachable by the runtime dashboard
19 +** Check if all flows have been installed according to the active release
20 +** Check if messages pass through the bus by verifying a critical message flow in external systems
24 24